The project for Engie involved the installation of the truss structure that supports a conveyor belt transporting products from ships to the Mejillones terminal.
For the expansion of Engie’s Maritime Terminal in Mejillones, 116 3.5-ton frames, a 42-meter-long, 44-ton gallery, and 36 7-ton frames were assembled. This assembly was carried out by the Yagana Crane Barge and the Compas Mars 1 multipurpose barge. The work was performed with high safety standards and in coordination with the ship’s arrival schedule at the ENGIE terminal.