One of the most critical aspects was the complete assembly of the south and north branches of the intake chamber, each weighing 158 tons. This work was performed with an accuracy of 20 centimeters along the axis, at a depth of 28 meters, demonstrating the team’s technical expertise.
Approximately 45 employees per shift participated in the execution of this project, along with engineering, technology, and intelligence teams, who provided innovative solutions to meet the required deadlines and standards.
The completion of this phase reaffirms our commitment to operational excellence and safety, consolidating our company’s position as a leader in highly complex maritime projects.